projects - infrastructure
references  
       

Sinabelkirchen - District heating

       
Project:
Fernwärme A-8261 Sinabelkirchen,
1,500 kW biomass und 800 kW oil

Scope of services:
Design and side supervision -heating/sanitary installations/district heat supply incl. boiler house and district heat supply lines
 
Technical data:
1. Stage of extension 1,500 KW
Final stage: 4,000 KW
Length of pipelines: 1.400 m
Pressure: 7 bar
Primary cycle: 90 C – 60 C

Construction period
7/2003 until autumn 2004

       

Abtenau - Cogeneration plant

       
Project:
Cogeneration plant Abtenau, Salzburg AG
Combinated heat and power generation through biomass
 
Scope of services:
Design, static calculation, site supervision, construction site coordination

Technical data:

6,000 kW thermal power
1,200 kW electric power via ORC-system
Boiler house: 1,300 m²

Construction period:
5/2004 until 12/2004
       

Altenmarkt - District heat

       
Project:
District heat supply of Altenmarkt and the company Atomic
 
Scope of services:
Design, static calculation, site supervision, construction, site coordination

Technical data:

Biomass cogeneration plant 5,000 kW thermal power (final stage 7,500 kW)
500 kW electric power via ORC-system
approx. 6,000 m public power supply

Construction period:
7/2004 bis 8/2005
       

Kaindorf - District heat

       
Project:
Biomass heating installation Kaindorf bei Hartberg
 
Scope of services:
Design and site supervision, refurbishment of the heating system

Technical data:

Total power: 320 kW
Energy saving per year:
approx. 65,000 kW (total)
Cost saving per year: approx. 2.300 €

Construction period:

2004
       

Hinterstoder - Local heat

       
Project:
District heat supply Hinterstoder, biomass district heating station (800 kW) and approx. 1.6 km public power supply
 
Scope of services:
Design, static calculation, site supervision

Technical data:

800 kW biomass boiler - winter
400 kW biomass boiler for fewer operation or covering peak operation
Boiler house: 110 m²
Storage of the wood chips: 300 m²

Construction period:
Spring 1998 – Winter 1998
       

Feldkirchen - Project study

       
Project:
Project study, A-9560 Feldkirchen i. Kärnten
 
Scope of services:
Study – district heating network

Techniscal data:

5,000 thermal power
Approx. 5,400 m length of pipelines
Approx. 5.9 bn. kWh energy consumption per year
Approx. 203,000 € saving of electricity costs per year

Construction period:
Spring – autumn 2006
       

Grabnerhof - Biomass district heating

       
Project:
Biomass district heating station incl. public power supply to Landwirtschaftliche Fachschule Grabnerhof
 
Scope of services:
Design, static calculation, site supervision

Technical data:

500 kW biomass boiler - winter
Boiler house: 105 m²
Storage of the wood chips: 300 m²
Length public power supply: approx. 400 m

Construction period:
8/1998 - 12/1998

       
       
 